Office
Location: Upstairs Status: In use, temporary floor needed
Current State
Section titled “Current State”- Chipboard flooring (needs replacing)
- Room is 2100x1700mm
- Currently in use (mentioned March 2025 as needing temporary floor)
Completed
Section titled “Completed”- Basic setup for work
- Temporary comfortable flooring (sock-friendly) - priority for work week
- Acoustic insulation between joists (paused)
- Final flooring (carpet or hard surface)
- Replace chipboard flooring properly
Furniture
Section titled “Furniture”- Grey desk (standing desk planned/discussed June 2025)
- IKEA desk moved to workshop
Floor Plan
Section titled “Floor Plan”- Temporary solution first (comfortable to walk on in socks)
- Later: acoustic insulation + proper floor finish
- Upstairs room
- Active use for work - needs livable floor sooner than other bedrooms