Location: Upstairs, main family bathroom Status: Completely gutted (April 2025)

  • Completely gutted (April 2025 strip-out)
  • Chipboard flooring (needs replacing)
  • Two basins removed, bath removed, toilet removed, bidet removed
  • Wallpaper stripped (Early March 2025)
  • Replace chipboard flooring
  • Plumbing installation (15mm feeds from utility/boiler cupboard)
  • Basin(s)
  • Bath
  • Toilet
  • Shower
  • Extractor fan (ducted to garage void, out through old boiler flue)
  • Floor finish (carpet or hard flooring)
  • Radiator
  • Decoration
  • 15mm hot/cold feeds from boiler cupboard in utility
  • Vertical feeds up from utility side
  • Tee locally for multiple fixtures
  • Extractor: 100mm duct dropping into garage ceiling space
  • Acoustic insulation between joists (Rockwool RWA45 or Knauf RS60)
  • Can be retrofitted by cutting access strips perpendicular to joists
  • Paused for now - prioritize downstairs livability first
  • One of two bathrooms upstairs (other is en-suite)
  • 35kw combi, long 15mm run from boiler
  • Bar shower planned