Tingles Restoration Timeline
Chronological overview of work completed.
March 2025
Section titled “March 2025”House Completion: 7 March 2025
Strip-Out (Early March)
- Wallpaper stripped: all downstairs + landing
- Fixtures removed: 2 toilets, 1 basin, 1 bidet, 1 bath
- Cooker, hob, hood removed for recycling
- Plastic sheeting laid on floors
- Skirting and gripper removed
- Four upstairs rooms still need wallpaper stripping
April 2025
Section titled “April 2025”Downstairs Floor Marathon (Early April - 3 days)
- 80m² completed over 3 days
- Build-up: 25mm PIR (Celotex TB4000) + 22mm Kronospan Fast Protect chipboard
- Rooms completed: living room, dining room, kitchen
- Hallway, downstairs toilet, study - final push needed
- Decision: glued + screwed (proper job)
- Block walls discovered between rooms (good for sound)
- Exhausted after marathon, decision to pause upstairs acoustic insulation
En-Suite Wet Room (All Month)
- Early: Damp remediation (base plate, expanding foam gaps)
- Tanking: full room with Mapei Mapelastic AquaDefense
- Aquapanel over backer board on walls
- Noggin frame between joists for tray support
- 1500x900mm wet room tray installed
- BIN primer under basin/toilet area (odour blocking)
- 21 April (worked till 10pm): Temporary LVT flooring laid in dry area, sanitary silicone seal, basin pipework cutouts
- 8mm backer board threshold installed
- Note: LVT later replaced with proper floor tiles + underfloor heating
Kitchen Planning
- 12 April: Original build debris found under kitchen units (core drill dust left for decades)
- 24 April: Kitchen redesign discussions - removing utility door, Wren kitchen ordered
- Decision: self-fit (not paying £6k for fitting)
Plumbing
- 26 April: Downstairs toilet pipework replacement planned (old pipework still in place)
- Expanding foam in wet room voids (priority - cold!)
- Radiators needed (wet room + downstairs toilet)
Electrical
- 17 April: Microwave sensor light sourced for downstairs toilet (blanking plate, live looped discussion - not yet installed)
May 2025
Section titled “May 2025”Early May
- 2 May: Garage shutter motor capacitor fixed (working with emergency-stop pendant)
Mid-Late May
- Wet room shower tray tile planning
- 1500x900mm tray = ~14.5 sq ft, ordered 16 sheets mosaic
June 2025
Section titled “June 2025”Wet Room Tiles
- Mineral Gris R11 mosaic ordered (4.8x4.8cm sheets)
- Padova Grey 600x600 for dry zone
- 11 June: Wall tile decisions, mosaic vs large format
- 21 June: Mosaic tiles laid (panicked - tiles twisted vs bathroom tiles, but placed shower screen there to hide)
Garage Planning
- 5 June: Serious garage conversion discussions
- 90% of way to habitable room (same build standard as house)
- 15 June: Mock Tudor facade inspection - light passing through timber, no insulation over garage
Kitchen Progress
- Wren kitchen spec finalized
- Shaker doors, oak worktops, undermount sink
- Self-fit decision firm (£8k units, avoiding £6k fitting quote)
Stress Management
- 11 June: “WiFi sorted, Green Star next, stressing about day job vs house work”
July 2025
Section titled “July 2025”Kitchen Continued
- 4 July: Surprisingly fit from house work (clearing drive, running stairs, lifting)
- 8 July: “Frankenhouse” revelation - three separate concrete slabs
- 14 July: Kitchen units going in, floor adjustments
External
- Patio cleaning
August 2025
Section titled “August 2025”Kitchen Work
- 18 August: Corner trim fitted (perfectly cut, piloted, screwed, glued)
- Sink sealed (fell on head during pipework work!)
- 21 August: Handle placement on Shaker doors discussed
Wall Prep
- 25 August: Wall filler shopping (Toupret, bonding, etc.)
- Old tile adhesive removal
Planning/Legal
- 25 August: Property boundary work, wall considerations
September 2025
Section titled “September 2025”Kitchen
- 13 September: Plastiflex skinning over old tiled wall portion (50% over worktop)
Ongoing
- 4 September: Mortgage overpayment vs renovation ROI discussions
October 2025
Section titled “October 2025”Garage Focus
- 13 October: Garage conversion becoming priority
- Fire separation discussion: easier to convert fully than keep as garage
- Pre-job overwhelm setting in
Plumbing
- 16 October: Manifold planning, radiator pipework
- 18-19 October: Radiator installation (back-to-back, dedicated pairs, proper manifold)
Kitchen
- Ongoing fitting work
November 2025
Section titled “November 2025”Critical Issues
- 13 November: Water leaks, garage roof
- Want to knock through hall to garage before winter
- 15 November: Mock Tudor facade investigation - needs complete redo
- Decision: wait till summer, strip back, rebuild properly
- Lead work on gable, timber replacement
- 25 November: Ordering floorboard, fireboard, plasterboard for repairs
December 2025
Section titled “December 2025”Legal Work
- Tingles legal dispute intensifies
- OCR of conveyance documents
- Case preparation
Kitchen Ongoing
- Still fitting
January 2026 (Current)
Section titled “January 2026 (Current)”Status Today (19 Jan)
- Kitchen 70% fitted
- En-suite wet room: floor and walls done, tiles pending
- Garage: roof leaking, conversion pending
- Downstairs floor: complete
- Upstairs: stripped, plastic sheets down, flooring pending
- Priority: get house warmer (radiators, insulation)
Key Decisions Made
Section titled “Key Decisions Made”| Decision | When | Rationale |
|---|---|---|
| Downstairs floor priority | March | Can’t live without it |
| Pause upstairs acoustic | March | Can retrofit later, need livable space now |
| Self-fit Wren kitchen | April | Save £6k, more control |
| Full garage conversion | October | Easier than fire-safe garage |
| Mock Tudor redo summer 2026 | November | Needs complete rebuild, wait for dry weather |