Cloakroom (Downstairs Toilet)

Location: Downstairs, external wall Above: Boiler cupboard on first floor

  • Floor raised ~47mm (PIR + chipboard to match rest of downstairs) (April 2025)
  • Old pipework still in place (replacement planned 26 April 2025)
  • Microwave sensor light sourced (not yet installed, discussed 17 April)
  • Floor insulation and buildup (matches rest of ground floor) (April 2025)
  • Pipework replacement for toilet and basin
  • Microwave sensor light installation
  • Toilet final installation (lifted 47mm to match new floor)
  • Basin final installation
  • Radiator
  • Toilet waste drops vertically through concrete slab
  • With 47mm floor raise, need flexible/offset pan connector
  • Basin waste through external wall
  • 15mm cold feed from utility trunk line
  • Use flexible or offset pan connector (McAlpine WC-F23R type)
  • Check pan doesn’t lift above soil pipe centre (needs downward fall)
  • Shim/platform under pan for level support
  • Route waste through external wall
  • Standard trap setup
  • Concrete floor with vertical soil pipe
  • External wall backing